Why the Sunshine Skyway Bridge Southbound Lanes Were Closed This Morning
If you were trying to make your way south of St. Petersburg this morning, it was a tough go of it when all southbound lanes were closed on the Sunshine Skyway Bridge at around mile marker 16. Erin Murray from Bay News 9 monitored the situation and posted to Twitter that a man driving a U-Haul truck came to a stop on the bridge at about 5AM.

File photo.
Knight / Beasley
If you were trying to make your way south of St. Petersburg this morning, it was a tough go of it when all southbound lanes were closed at around 5am on the Sunshine Skyway Bridge. Erin Murray from Bay News 9 monitored the situation and posted to Twitter that a man climbed to the top of a parked U-Haul truck and sat. She says emergency crews came to the scene and were able to get him down safely. ABC Action News tweeted that he was put into a patrol car. Lanes reopened sometime around 8am.
Also trending today...
Updated June 2024
As you drive over the Howard Frankland Bridge, you see progress, but it's still pretty tough to imagine what all of this work is going to look like upon completion. Work won't finish until late 2025 according to the Florida Department of Transportation. The cost is expected to be about $865 million. Not patient enough to wait until 2025 to see what this is all going to look like? Nor am I. Here's a sneak preview from artist renditions shared by the Florida Department of Transportation.
A new southbound/westbound (from Tampa to St. Pete) bridge is what you see currently being built north of the current southbound/westbound bridge. It'll have 8 lanes - 4 for general use and 4 express lanes. There's a bike and pedestrian path in the plan. The bridge we use now to go from Tampa to St. Pete will become the new northbound/eastbound part of 275 once the new bridge is ready. The bridge we use to go from St. Pete to Tampa will be taken down.
Bridge Progress
As of May 2024:
- 100% of pilings have been driven.
- 99% of bridge footings have been completed.
- 98% of bridge columns have been completed.
- 92% of bridge caps have been completed.
- 77% of the bridge superstructure beams have been placed.
- 71% of bridge decks placed.
Not only are they making major progress on the structure of the bridge. But they have also finally repaved the 2 right lanes by the Martin Luther King JR exit. I'd imagine that the nice weather and lack of rain has helped them get some of this progress completed.
Many complain that this won't help with our traffic flow, especially with the malfunction junction exit going into the Veteran's/Clearwater. Well, don't worry. The FDOT is on that too, as apart of the Westshore Interchange reconstruction project.
Here's what a completed Howard Frankland Bridge will look like plus some updated photos from May 2024
Artist rendition of overlook w ITS

Artist rendition with traffic

Artist rendition of overlook

Artist rendition

Artist rendition of pedestrian feature

Howard Frankland Bridge May 2024 Update

Howard Frankland Bridge May 2024 Update

Howard Frankland Bridge May 2024 Update

Howard Frankland Bridge May 2024 Update